National Coal Logistics
Coal Wagon Age-Based SM Framework
Improving predictability, efficiency and cost effectivenessof Scheduled Maintenance activities.
Challenges & Context
Our client operate a diverse fleet of haulage wagons across their Australian rail network. As some of their coal wagon fleet approaches the midway point of its lifecycle, unplanned parts and labour requirements placed additional risk into the Scheduled Maintenance (SM) program.
Our client engaged Untapped to build an age-based SM program, forecasting parts and labour requirements into repeatable job plans.
Focus areas included:
- Material requirements
- Labour forecasting
- Component replacement based on historical data
- Repeatable job plans and inspection sheets
Approach
A phased approach was designed to build an SM framework from historical data, allowing the client distinct approval and engagement points to ensure the solution was owned and implemented.
Significant data analysis was undertaken to identify material usage aligning with the SM frequency of 3 to 4 years. Key materials were identified and their optimum planned quantities captured. This formed a series of future component plans.
Labour requirements were established for these component replacements. Cost models were built to forecast labour and material spend over the remaining life.
Once component replacement was finalised, visual inspection and measurement tasks were identified using the maintenance manual library, and converted into service sheets for each SM frequency.
Outcomes
Forward planning of component replacements allow:
- Budgeting
- Forecast of materials for suppliers
- Labour requirements
- Labour levelling across other wagon fleets
Building inspection sheets creates:
- Consistent application of the maintenance manuals for each scheduled maintenance activity
- Accountability of maintainers at sign off
- Clearer direction for maintainers of what inspection or measurement tasks are required