Critical Minerals Mining Panel Relocation Plans

Baseline relocation documentation improves safety, strengthens planning and reduces downtime.


Australian Miner


NSW, Australia


2025 - 2026


Challenges & Context

Equipment relocation is a recurring requirement at our client’s mine in south-western New South Wales. The operation uses specialised horizontal directional drilling rigs, supported by mud processing facilities known as “Mud City” and Mobile Mining Plants (MMPs). As mining progresses, these assets must move between drill locations and mining panels. Our client engaged Untapped to develop a consistent approach to these moves, with clear task sequencing, labour and tooling requirements, and safety considerations to help minimise production downtime.


As a greenfield operation, the operations equipment layouts, work practices and resource requirements were still evolving. Each asset presented different planning challenges, including changes to Mud City positioning and the effect of spare sump availability on MMP relocation duration. The documentation needed to capture current knowledge while remaining adaptable as the site gained operating experience.


Approach

Untapped combined field observation, stakeholder consultation and technical document review across three site visits between September 2025 and March 2026. We inspected equipment, observed two drill rig relocations, participated in relocation planning and execution exercises, and gathered input from drilling crews, maintenance, projects and planning personnel. Existing drawings, schedules, design reports and original equipment manufacturer information provided the technical foundation for the work.


For each asset type, we developed linked Gantt schedules, task and resource summaries, and full relocation procedures, supported by in-field images. Alternative schedules addressed one-off layout transitions and moves, with and without spare infrastructure. Drill rig deliverables also captured lessons learnt and maintenance opportunities that could be completed alongside relocation work. Draft documents were issued for stakeholder review and refined using relocation feedback where available, with a structured feedback form established to support future updates.


Outcomes

Our client received a coordinated baseline documentation suite covering drill rigs, Mud City and MMP relocations. The packages bring task sequencing, resourcing and procedural guidance together, providing a repeatable foundation for planning future moves. Drill rig and Mud City documentation incorporated feedback from actual relocation activities, while the alternative MMP schedules provided a basis for assessing the operational implications of spare sump availability. All documents were handed over in final-draft status for Iluka’s approval.


The engagement also identified practical opportunities to strengthen relocation delivery, including further development of safety documentation, follow-through on isolation and tooling improvements, clearer allocation of responsibilities, and better use of SAP to coordinate relocations with maintenance. Together, the deliverables and improvement opportunities established a foundation for more consistent relocation planning and ongoing refinement as the mine moves towards steady-state production.

Explore More of Our Work

Large industrial turbine with curved metal blades and yellow machinery components in a factory setting.
26 November 2026
Our client’s Pilbara operations require experienced maintenance planners and schedulers to maintain work readiness and support maintenance execution. Attracting and retaining skilled practitioners, covering leave and vacancies, and responding to changing workloads creates ongoing resource pressures.
26 November 2026
Improving predictability, efficiency and cost effectiveness of Scheduled Maintenance activities.
26 November 2026
Asset inspections to deliver improved SAP master data, compliance and management of assets.