Shutdown Leading Practice

Embedding leading practices to improve shutdown performance.


International Miner


Pilbara, Western Australia, Australia


Aug 2025 to Sept 2026


Challenges & Context

The client identified a significant opportunity to improve fixed-plant shutdown performance across its Pilbara operations. Shutdown overrun hours had increased by 49% since 2018, while resourcing levels exceeded requirements by up to 30%. The source estimated that overruns and excess labour represented a potential annual cost exposure of up to $694 million.


Washdowns, permitting and scheduling accounted for more than 75% of activity delays. Although a shutdown procedure and leading-practice playbook were in place, site practices varied and were not consistently embedded in day-to-day work.


For example, three versions of the wash sheet were in use, wash plans were not aligned with the Gantt schedule, ownership was unclear, and sign-off was inconsistent.



Approach

Embedded Shutdown Advisors focused on frontline execution and targeted coaching, with particular emphasis on leadership, mindsets and behaviours.


Working within each site’s shutdown planning and execution teams across the full shutdown cycle—from T‑13 through to the post-shutdown review—coaches used structured field observations, stakeholder interviews and site process reviews to identify gaps against the shutdown playbook’s winning conditions.


Shutdown Coaches engaged shutdown, maintenance, operations and planning Superintendents and Managers to agree priorities and take ownership of tailored improvement actions. Site teams were coached to adopt and sustain the seven leading practices, with actions maintained in the shutdown improvement register and progress reported from one shutdown to the next. Successful practices from one site were captured and replicated across the operations.


Outcomes

A measurable improvement in shutdown performance, owned by site teams and sustained beyond the coaching engagement.

  • Reduced shutdown overrun hours and more efficient resourcing.
  • Improved safety, productivity, quality and cost performance.
  • Progressive improvement in shutdown maturity from one shutdown to the next.
  • Process conformance maintained at or above the 85% target.
  • Improvement actions completed and owned by site teams.
  • Sustained site capability built through observation, coaching and influence.

Explore More of Our Work

Large industrial turbine with curved metal blades and yellow machinery components in a factory setting.
26 November 2026
Our client’s Pilbara operations require experienced maintenance planners and schedulers to maintain work readiness and support maintenance execution. Attracting and retaining skilled practitioners, covering leave and vacancies, and responding to changing workloads creates ongoing resource pressures.
26 November 2026
Improving predictability, efficiency and cost effectiveness of Scheduled Maintenance activities.
26 November 2026
Asset inspections to deliver improved SAP master data, compliance and management of assets.